top of page

BURGESS HILL RECYCLING CENTRE

This reinforced retaining wall had to be constructed within the recycling shed due to a large section of the wall being removed because of fire damage.

 

The wall was 3 meters high by 30 meters long and was completed in under 2 weeks. This was a very difficult task due to lack of roof height for cranage and limited space behind the back walls.  

bottom of page